IJACK XFER Trial

CanERIC Program

2022

 

Executive Summary

Test has concluded. Tri-phase pump was installed at 03-32-004-05W2. Tri-phase pump was installed March 16, 2021. Installation costs, equipment rental, and fuel costs over the 4-month trial were on budget. The test was a success. Installing the tri-phase pump reduced upstream pipeline pressure by 250 psi. This reduction in pressure is the same as what a Satellite Facility would have achieved, however the tri-phase pump allows conservation of all produced gas volumes, whereby a Satellite Facility would have required volumes to be flared. Conserved gas volumes: 2.8 E3m3/d.

 

CanERIC Final Report – Final Milestone Report